2009年8月28日 星期五

Green Management in Government

Adoption of Energy Efficient Features and Renewable Energy Technologies in Government Projects and Installations
4. Maps of mean wind power density for Hong Kong
6. General information on renewable energy
·  Leaflet about renewable energy in pdf format
·  Relevant page in EnergyLand website

7. Stage 1 Study Report on the Potential Applications of Renewable Energy in Hong Kong

·  Chapter 5 Solar Energy in pdf format
·  Chapter 6 Wind Energy in pdf format
·  Chapter 8 Energy-from-waste in pdf format

8. Technical Guidelines on Grid Connection of Renewable Energy Power Systems

·  Technical Guidelines in pdf format

9. General Specifications, Circulars and Instructions issued by ArchSD relating to the promotion of energy efficiency and renewable energy
·  General Specification for Electrical Installation in Government Buildings, 2007 Edition
·  General Specification for Lift and Escalator and Passenger Conveyor Installation in Government Buildings, 2007 Edition
·  Circular No. 11 of 2003 – Use of High Output T5 Flurorescent Luminiares for High Bay Lighting Applications
·  Circular No.45 of 2003 – Introduction to Renewable and Clean Energy Technology
·  Circular No.5 of 2004 – Study Report on Selection of Energy Efficient and Cost Effective Luminaires
·  Circular No.6 of 2004 – Study Report on Use of Heat Pump in lieu of Traditional Hot Water Heaters and Criteria for Installation of Thermal Wheels & Heat Recovery Chillers for Projects
·  Circular No. 32 of 2005 - Guidelines on Wider Use of Renewable Energy Technologies and Energy Efficient Features in Building Projects
·  Circular No. 10 of 2006 - Study on the performance of BIPV System at Castle Peak Hospital
·  Circular No. 8 of 2007 - Design Tool Kit for Small Scale Building Integrated Photovoltaic Applications
·  >Operating Instruction 03/2001 – Overall Energy Approach
·  Operating Instruction 02/2004 – Cost Analysis for Renewable Energy and Clean Energy Applications
·  Operating Instruction 18/2006 - Adoption of Energy Efficient Features and Renewable Energy Technologies
10. Forum on ETWB Technical Circular (Works) 16/2005 (3 May 2006 & 5 June 2006)
·  Invitation to works departments
·  Reply form
·  Technical Circular (Works) 16/2005
·  Presentation materials on EE & RE technologies
·  Presentation materials on Building Energy Codes
11. Application Guides on Energy Efficient Features for ETWB TC(W) No.16/2005
Given below are application guides for some commonly used energy efficient technologies listed in the technical circular.
·  AG01 - Occupancy Sensor Control for General Lighting System
·  AG03 - Cooling Tower for Heat Rejection of Air Conditioning System
·  AG04 - Secondary Chilled Water Distribution in Air Conditioning System
·  AG05 - Energy Management System for Energy Consumption Check
·  AG06 - Occupany Sensor Control for Escalator
·  AG07 - Low Energy Consumption Signs
·  AG08 - Application Guide on High Efficiency Motors
·  AG09 - Guidelines on Programmable On/Off Control for Lighting and Air Conditioning System
·  AG10 - Adopting Heat Recovery Chillers for Reclaiming Waste Heat in Air Conditioning System
·  AG11 - Adopting Demand Control of Fresh Air in Air Conditioning System

Hong Kong Awards for Energy Efficiency and Conservation in Government
1.            Prize Presentation Ceremony (Chinese version only)
2.            Speech by Officiating Guest at Prize Presentation Ceremony (Chinese version only)
3.            List of Winners
Energy save tip

Briefing Sessions on Government Energy Consumption Reporting and Monitoring by EMSD (July 2009) 
1. Government Energy Consumption Reporting and Monitoring
2. Management of Electricity Accounts (CLP)
3. Management of Electricity Accounts (HKE)
4. Management of Towngas Accounts (Towngas) 


Energy Efficiency and Conservation
in Government
Experience Sharing
organized by EMSD (May 2004)
 
 
Presentation 1 : Leisure and Cultural Services Department 
Presentation 2 : Tuen Mun Government Primary School 
Presentation 2a: Tuen Mun Government Primary School (Movie a) 
Presentation 2b: Tuen Mun Government Primary School (Movie b) 
Presentation 3 : Hong Yip Service Company Limited 
Presentation 4 : Hong Kong Productivity Council 
Presentation 5 : Fire Services Department 
Presentation 6 : Civil Engineering Department 

2009年8月15日 星期六

8.8台灣水災

...「莫拉克」前日正面吹襲台灣時,南部受災嚴重,高雄錄得二千多毫米的驚人雨量(比香港黑雨警告大二三十倍),多處發生泥石流。其中甲仙鄉小林村災情慘重,全村一千三百多人,據了解僅有四十多人逃出,另百多人獲救,初步估計還有約千人可能被活埋。附近的那瑪夏、桃源、六龜、茂林等山地鄉約十多村莊亦失去聯絡,數千鄉民受困待援。...


根據台灣 "中央氣象局" 8/8及9/8逐日雨量資料:
高雄每小時最高降水量52mm/hr (8/8 6:00),兩天降水量216.5(7/8)+507 (8/8)=723.5mm
阿里山每小時最高降水量 123mm/hr (9/8 2:00),兩天降水量1161.5(8/8)+1165.5 (9/8)=2327mm
By Horner's equation, the design intensity i = a / (td+b)^c where parameters a,b & c subject to different districts in Taiwan (水資源局”水文設計應用手冊”)
For return period (T) =200 years and duration (td) =30 min, 高雄 i = 164.3 mm/hr and 阿里山 i = 145.3 mm/hr.
For T=50 years and td =30 min, 高雄 i = 124.8 mm/hr and 阿里山 i = 113 mm/hr.
How about in HK? According to the Flood Protection Standards in Hong Kong, the design return period for urban drainage truck system is 200 years and for urban branch system is 50 years.
The design intensity i may be calculated according to DSD's manual 4.3.2 and such parameters a,b & c based on Table 3 by 'Gumbel solution'. Design intensity i = a / (td+b)^c.
For T=200 years and td=30min. , i = 187mm/hr; and T=50 years, i = 156mm/hr
Design intensity (i) both in HK and Taiwan seem to be marginally satisfied with the extreme hourly rainfall. How about the long duration of rainfall?
According to DSD's Technical Manuals Table 4, the extreme depth x (mm) for various return years (T) based on hourly records measured at HKO (1884 – 1939 ; 1947 – 1990) and as follows:-
i) For T=200 years, x = 622mm/day or 729mm (2 days) <2327mm (阿里山) or 723mm (高雄)
ii) For T=50 years, x = 507mm/day or 595mm (2 days)
The flooding in Taiwan is obviously as a result of the extreme duration of rainfall and accumulated surface runoff. (The discussion of design duration of rainfall may be referred to DSD's flood prevention Q&A and administration response to Legco on projects 22CD & 81CD.)
In HKO's record, the highest daily rainfall is 534.1mm/day at 19 Jul 1926 and the highest hourly rainfall is 109.9mm/hr at 8 May 1992. Black rainstorm warning when rainfall >70mm/hr.
HKO study found that under the influence of global warming, annual rainfall in Hong Kong would increase at a rate of about 1% each decade in the 21st century - about the same rate as in the past 120 years.
香港年雨量過去變化及未來推算
Other Information:

2009年8月12日 星期三

計算用電量

用電量計算: 1kW x 1小時 (千瓦時 kWh) =1度電
能量 E (J)= 功率 P x 時間 t (W x s)
(P = 電流 I x 伏特 V)
(1kWh = 3,600,000J)
例如一只25w的電燈泡每天開4小時。
每天用電量 = 25 x 4 / 1000 = 0.1kWh 即0.1度電
如每度電 $0.9, 即每天電費約 0.1 x $0.9 = $0.09/日,全年約$0.09 x 365日 = $32.9
CLP 能源計算機
https://www.clpgroup.com/poweru/chi/energy_calculator/index.aspx
WWF低碳生活電器選購指南

2009年8月4日 星期二

可持續發展回應文件

可持續發展回應文件
1. 建築間距
建議方案北京、成都和廣州等內地上海
地盤面積大於2公頃的或連續闊度超過60米的建築物,須留有相當於建築物正面外牆總面積20%33.3%的間隔空間。城市強制規定緊密相連的高樓大廈的闊度和建築群之間的最小間距,以日照規定。
面向河流的建築物實施強制規定,只容許「尖塔」式的建築,而尖塔之間亦有最小間距限制。不同城市的做法略有差別。
 
強制措施,為相連的臨街建築群最大闊度提供指引。高度低於或相等於24米、建築闊度為80米或以上的建築物,必須相距最少6米。

2. 樓宇後移
建議方案內地東京紐約新加坡
這項方案建議在不足15米闊的街道,把新建築發展項目由地面至15米高部分後移退入,使街道中央至建築物之間的闊度不少於 7.5米。主要城市,強制採用類似的樓宇後移管制政策。強制規定樓宇後移,並參照附近道路的闊度和分區管制執行。分區規劃是規定根據鄰接的街道闊度來設定「初步後移距離」。實施鼓勵措施。在符合若干標準的情況下,地面行人路網絡的有蓋公共空間也可獲豁免計入總樓面面積。


3. 市區綠化
建議方案內地東京紐約新加坡
面積大於1,000平方米的地盤必須進行綠化,並劃撥20%30%的面積,包括地面、平台和屋頂為固定綠化用地。多個主要城市,建築法規訂明在新區的所有新住宅發展地盤要達到最少30%的綠化地。在舊城區,由於空間所限,規定的最小綠化面積約為地盤的20%25%屋頂綠化措施(Green Rooftops Initiatives)強制規定新落成的建築物如地盤面積超過0.1公頃(公共設施地盤面積則為250平方米以上),則最少要有20%的屋頂用作綠化。《高效益建築物指引(High Performance Building Guidelines)規定新的公共建築物必須就約每100平方米的不滲漏表面,在地盤範圍內種植最少一棵樹。地面的美化空間如被建築物、樓層或屋簷遮蓋,則可獲豁免計入總樓面面積。(i) 豁免上限為伸出物邊緣起計45度,而在此45度直線內的公共美化空間必須為非密封及可供公眾使用。(ii)屬於高空平台一部分但在45度直線以外的其餘範圍可獲得額外總樓面面積寬免,最多達樓面面積的20%,但有關的高空平台在45度直線以內的面積必須佔樓面面積最少60%,而高空平台樓層的邊緣必須最少有60%為矮牆設計。
相關資料:
a. 顧問研究 : 對應香港可持續都市生活空間之建築設計
b. Publication for Plan New York 2030
c. Sustainable Signapore

4. 檢討現行的總樓面面積寛免規定:-
A. 根據《建築物(規劃)規例(“《條例》”) (123 章附屬法例F) 23(3)(b)23A(3)PNAP13不計算的總樓面面積
項目設施
是否強制提供此項設施
空間設計方面的強制規定
1水箱機電房、電掣房、電錶房、電力變壓房、發電機房、泵房、直立電纜管道房、二氧化碳房、消防喉轆間、污水處理機房、中央通風或排煙系統井道
電力裝置須符合電力公司有關供電規則的空間規定 (詳見CLPHKE綱址及《香港規劃標準與準則》第七章2)
消防裝置的規格須按照《最低限度之消防裝置及設備守則》、《裝置及設備之檢查、測試及保養守則》所訂的標準
其他設施在空間設計方面並無強制規定
2消防員升降機和殘疾人士升降機的升降機機房
有關設施須符合《建築物(建造)規例》9A的規定,並符合《升降機與自動梯建築工程守則》及PNAP207的空間規定
3消防員升降機和殘疾人士升降機以外的其他升降機的機房
如提供有關設施,該等設施須符合《建築物(建造)規例》9A的規定,並符合《升降機與自動梯建築工程守則》及PNAP207的空間規定
4空調機房(包括爐房)
(酒店的中央空調機除外, PNAP111)
空間設計方面並無強制規定
(PNAP13: 空調房面積<GFA1%鮮風櫃<該層GFA4%,否則需提供機電佈置圖)
 
5停車場及上落客貨區須按照《香港規劃標準與準則》訂明的最低標準及租地條件
 
1.        須符合《規劃標準》第八章7節及PNAP236訂明的標準尺寸;
2.        任何在露天場地或露天屋面平台的停泊車位(不限私家或公共車位);
3.        除規劃局要求,公共交通總站(PPT)均不獲寬減;
4.        上落客貨區在私家停泊車位可寬免,見PNAP13
6垃圾及物料回收房
須符合《建築物(垃圾及物料回收房及垃圾槽)規例》和相關的作業備考訂明的最低空間規定 (例如《規劃標準》第九章6.2.15節及PNAP98)
7貫通不計算總樓面面積的樓層的樓梯和升降機槽的水平面積
空間設計方面並無最低規定
(PNAP1311)
8電訊及廣播設備室
有關設施須符合《規例》28A 條的規定,並符合相關的作業備考訂明的空間規定(例如PNAP201電訊標準)
9酒店的後勤設施
除非申請人根據《規例》23A申請獲得旅館發展寬免,否則不屬於強制規定。旅館地盤的批地條件也可能規定須提供後勤設施。)
空間設計方面並無最低規定

B. 根據《建築物條例》(“《條例》”) (123 )42獲寬免的總樓面面積 (有關適意設施見PNAP116)
項目設施
是否強制提供此項設施
空間設計方面的強制規定
1聯合作備考》第1和第2號所載的環保設施包括:
𠁹 露台* (只適用於客飯廳,豁免面積2m²4%實用空間,但<5m²)
𠁹 加闊的公用走廊及升降機大堂*
l            只適用於住宅樓宇入口處大堂以外的樓層;
l            假如沒有提供天然通風但提供機械通風, 則走廊需介乎1200-1800毫米闊, 而升降機大堂需介乎1650-2200毫米闊, 方可獲得豁免;
l            假如設有天然通風,則走廊需介乎1200-2200毫米闊, 而升降機大堂需介乎1650-2500毫米闊, 方可獲得豁免。
𠁹 遮陽篷* (外牆伸出<1.5m)
𠁹 空中花園 (>1/3樓面面積;第一個位於地面以上10層或以下樓層;淨高>4.5m;栽種面積>25%)
𠁹 平台花園 (屬商業或工業塔式大廈的樓層底部範圍內; 淨高>4.5m;栽種面積>25%)
𠁹 隔聲鰭* (外牆伸出<1.5m)
𠁹 翼牆、捕風器及風斗*(外牆伸出<1.5m)
𠁹 工作平台 (<1.5m² 通風良好;不可與同一單位內的任何露台相連)
𠁹 設有郵箱的郵件派遞室* (建議郵箱尺寸為100mmx300mmx400mm(深度); 派遞室通道<1.2m)
𠁹 非結構預製外牆 (<300mm)
𠁹 隔音屏障
* 此類環保設施可獲豁免的累積總樓面面積,不得超逾發展項目獲准的合計總樓面面積的8%
不適用
2喉管槽
不適用
3避火處
須符合《1996年提供火警逃生途徑守則》訂明的空間規定
4康樂設施
(例如:會所、壁球場、健身室、多用途室等)
(註:每個發展項目的康樂設施的寬免面積的上限為住用總樓面面積的5%)
不適用
5有蓋花園/遊樂場地
 
6平面隔板/有蓋行人道
 
7游泳池的濾水器機房
(如有提供游泳池,有關設施屬於強制規定)
空間設計方面並無最低規定
8櫃位、亭子、辦公室貯物用地、守衞室、供看更和管理人員使用的洗手間
不適用
9大型工、商樓宇的郵件室
不適用
10較大的升降機槽
不適用
11多層住宅樓宇內的小型後勤服務室
不適用
12主要大堂入口上方的空間
不適用
13在電影院、劇院樓座、銀行大堂、商場等前方的空間
不適用
14複式單位及單一家庭洋房的樓板中空
不適用
15在建築物內或穿過建築物,並位於地面水平或其他樓層而撥供作
公眾通道的地方
除非規劃條件或批地契約有所要求,否則不屬強制規定
空間設計的規定,視乎有關政府部門需要或接納用作公眾通道的範圍而定

C. 根據《規例》22獲得的額外總樓面面積
項目設施
是否強制提供此項設施
空間設計方面的強制規定
1位於地面水平,向後退入以撥供作公眾通道的地方(街道擴闊)
除非規劃條件或批地契約有所要求,否則不屬強制規定
空間設計的規定,視乎所需的街道擴闊範圍及預計人流而定
2交回位於地面水平的土地作為街道擴闊之用除非規劃條件或批地契約有所要求,否則不屬強制規定空間設計的規定,視乎街道擴闊所需的土地範圍而定
詳見可可持續發展委員會網址: http://www.susdev.org.hk/b5/knowledge.aspx
“豁免總樓面面積”是根據《建築物條例》( 第123 章) 第42(1)條而批出。此條文訂明, 如建築事務監督認為情況特殊, 可在接獲有關申請和收到列明的費用後, 以書面通知修訂條例的條文。建築事務監督可在接獲申請及訂明費用後行使此權力, 就若干設施豁免計算總樓面面積, 包括環保設施及完善生活設施, 例如露台、空間等。就不同設施而批出豁免總樓面面積的準則, 已在相關的作業備考中訂明。
“不計算的總樓面面積”列載於《建築物( 規劃) 規例》( 第123 章附屬法例F) 第23(3)(b)和23A(3)。建築事務監督如認為任何樓面面積僅用以興建或擬用作停車場、垃圾房或獲建築事務監督許可的其他支援設施等用途, 則可不計算有關樓面面積。“額外總樓面面積”列載於《建築物( 規劃) 規例》( 第123 章附屬法例F) 第22 條。如政府同意接收/徵用建築物向後移而騰出的地面空間, 用以設立公共通道或擴闊道路的土地, 則可批出相當於有關土地面積五倍或許可地積比率20%以下( 以較少者為準) 的額外總樓面面積, 作為把私人用地撥作公共用途的補償。對於在地面水平或其他樓層把穿越建築物的空間撥作公共通道的範圍, 建築事務監督亦可根據《建築物條例》(第123 章)第42(1)條的方式批准寬免。

其它網址:
i. 效能守則
ii. 建築物能源效益資助計劃
iii. 提倡能源效益及節約-- 機電工程署
iv. 香港節能網
v. 香港可持續科技網
vi. The Budget - HKSAR
vii. Environmental Impact Assessment Ordinance (EIAO) for 'designated project' - EPD
viii. 就樓宇獲批的總樓面面積寬免而進行的一項抽樣研究