Comparison of Jacked and Driven H-pile
Type |
Jacked Pile
( ArchSD’s PS(1) and VLA (2011)(2) )
|
Driven H-Pile
(COP of Foundation(3) and BD’s EM 2.1.13(4) )
|
1. Design requirement
| ||
Working load
(WL = 0.33Ys):
i) 305x305x180kg/m
ii) 305x305x223kg/m
|
For grade 55C
2950kN
3450kN
|
For grade 55C
2950kN
3450kN
|
Pile group reduction for group of 5 piles for spacing 3 times circumscribed rectangles of H-piles
|
0.85
|
0.85
|
Founding of pile
|
SPT N-value may less than 200
|
i) SPT N-value ³ 210 for 305´305´223 kg/m H-piles
ii) SPT N-value ³ 180 for other H-piles
(BD EM
|
Settlement analysis
|
More than 10 piles
|
No specify
|
2. Installation
| ||
Maximum jack force
|
(i) Not exceed 90% of total weight of the pile-jacking machine; and
(ii) 80% of yield stress of H-pile
|
N/A
|
Calibration of hydraulic jack
|
(i) Calibrated by HOKLAS by calibrated load cell;
(ii) Re-calibration at a force of 2.2.WL shall be carried out after jacking every 30 piles or repair.
|
N/A
|
Monitoring of jacking force
|
e.g. Pile Driving Monitor (PDM) developed by Inopiles International Pte Ltd.
|
N/A
|
Prevention of pile buckling
|
Gaps between the H-pile and pile hole shall be kept filled up with sand
|
N/A
|
Storage of spliced piles
|
To avoid idling time, several pieces of piles will be welded and stored into bored hollow shaft vertically
|
N/A
|
3. Termination procedures and criteria
| ||
Pre-creeping by pre-loading process
|
(i) Before termination of pile, at least 2.3WL for suitable period determined by contractor
(ii) At 10% of piles (min. 5 piles) to be carried out by pre-loading test: 2.2WL until the settlement rate is less than 5mm per 15 minutes
|
N/A
|
4. Verification
| ||
Trial pile
|
Subject to static loading test
(6.11 of PS)
|
Depend on actual site condition. e.g. for short pile
(BD EM 2.1.4)
not less than 2 testing pile which rest on bedrock
(5.4.11 (4) of COP) |
Verification test
|
The Contractor shall demonstrate with PDA analysis that driving stresses would not exceed 0.9 fy.
(clause 5.18(iv) of GS)
|
The integrity and capacity of at least 10% of the working piles should be verified by PDA tests.
|
No of piles for loading test
|
1% minimum one pile or more
(clause 5.28(ii) to (iv) of GS)
|
1% & at least 1 no of piles
(BD EM2.1.6 & 2.1.11)
|
Loading test
(where P = 2WL)
|
1st cycle: 0->0.25P->0.5P-> 0.25P->0
2nd cycle: 0->0.25P->0.5P-> 0.75P->P (72 hrs)->0.75P-> 0.5P-> 0.25P->0
|
1st cycle: 0->0.25P->0.5P-> 0.25P->0
2nd cycle: 0->0.25P->0.5P-> 0.75P->P (72 hrs)->0.75P-> 0.5P-> 0.25P->0
|
Settlement of loading test
|
(i) Total settlement = P/AE + D/120 + 4 mm
(ii) Residual settlement = D/120 + 4 mm; and
25% of the maximum pile head
settlement during the test,
whichever is the greater.
where:
D = Diameter of circular pile in mm, or = The least lateral dimension of steel 'H' pile section in mm (for driven steel 'H' pile )
P = 2WL Test load
L = Nett length of pile (For piles with rock sockets, L shall be measured to the center of the rock socket.)
A = Cross sectional area of pile
E = Young's modulus of pile given below:
|
Same as ArchSD’GS
|
Reference:
4. Engineering Manual issued by BD;