2013年3月6日 星期三

Recent Railway Development in HK



(Photo from:
http://www.idomin.com/news/articleView.html?idxno=400953)

I. Background

Railway is the backbone of Hong Kong's passenger transport system. At present, there has ten railway lines in Hong Kong. They carry over 4.5 million passengers per day. The number is occupancy 38% of all daily transport passengers in Hong Kong.

Now, five strategic railway lines recommended in the Railway Development Strategy 2000 is undergoing. They include the West Island Line (WIL), Hong Kong Section of the Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL), South Island Line (East) (SIL(E)), Kwun Tong Line Extension (KTL) and Shatin to Central Link (SCL). These five railway projects will be completed between 2014 and 2020.




II. Public engagements (reference: HyD’s website)
Recently, the Government is reviewing and updating the Railway Development Strategy 2000. Two public engagements were conducted on July 2012 and May 2013. The first public engagement is focus on the major regional railway corridors, which include the Hong Kong-Shenzhen Western Express Line, Northern Link and Coastal Railway between Tuen Mun and Tsuen Wan. Moreover, seven local enhancements are suggested according to the findings of the public expectations and the statistic analysis in the second public engagement. They include North Island Line (NIL), Siu Sai Wan Line (SSWL), South Island Line (West) (SIL(W)), Tuen Mun South Extension, Hung Shui Kiu Station, Tunf Chung West Extension and Kwu Tung Station. 

II. Information for Shatin Central Link (SCL)
A. Legislative Council
2. The construction cost is estimated to be $79.8 billion (MOD).
B. Highways Department:
4. Cover Story - “Shatin to Central Link (SCL) Snapshots”, Highways Department Newsletter Issue 2/2012;
5. “The Shatin to Central Link and Kwun Tong Line Extension”, Highways Department Newsletter Issue 2/2008
6. XPS
C. MTRCL:
D. Environment and Heritage Preservation
1. The SCL will pass below some historic buildings, including three historical structures at the former Tai Hom Village (the old pillbox, the former Royal Airforce hangar and the stone house) which will have to be temporarily dismantled and relocated during the project’s construction, and archaeology site in Kai Tak.
2. Environmental Impact Assessment for SCL from EPD

E. News about XRL & SCL
XRL news 高鐵有關新聞 :-
.   2013.11.7 - 高鐵香港段國產列車 初次曝光 - 東方日報
.   2013.10.18 - 高鐵申索額75.6億佔合約17% - 東方日報
.   2013.9.3 - 高鐵徵地地署死撐符市值 - 東方日報
.   2013.8.27 - 高鐵工潮解決 抗爭十四小時 - 東方日報
.   2013.8.24 - 吊機打翻工作台兩人傷 - 東方日報
.   2013.8.3 - 高鐵隧道塌泥險葬工程師 - 東方日報;
.   2013.8.29 - 樁錘擊背 巴裔地盤工命危 - 東方日報
.   2013.7.13 - 沙中線工程惹地裂疑雲 - 東方日報;


F. Other information from Internet
7. “MTR orders trains and signalling for Shatin – Central Link” posted by IRJ
8. 電車公司啟德現代化電車(詳細計劃文件)

Annex A. List of contract awards from MTRCL’s websites (or MTRCL's Notice) as of April 2014

Contract No.Contract NameContractorContract Amount (in HK$)Contract Award Date
1101Modification of Ma On Shan LineSun Fook Kong Joint Venture$620,000,00011 July 2012
1102Hin Keng Station and Approach StructuresPenta-Ocean Construction Co. Ltd.$1,039,000,0005 July 2013
1103Hin Keng to Diamond Hill tunnels and Fung Tak Public Transport InterchangeVINCI Construction Grands Projets$2,727,891,80516 October 2012
1106Diamond Hill Station ExtensionLeader Joint Venture$1,665,080,88813 December 2012
1107Diamond Hill to Kai Tak TunnelsChun Wo - SELI Joint Venture$1,067,338,0007 March 2013
1108Kai Tak Station and Associated TunnelsKaden - Chun Wo Joint Venture$1,422,000,00025 April 2013
1108AKai Tak Barging Point FacilitiesConcentric - Hong Kong River Joint Venture$289,993,39810 August 2012
1109Stations and Tunnels of Kowloon City SectionSamsung - Hsin Chong Joint Venture $4,569,503,00011 July 2012
1111Hung Hom North Approach TunnelsGammon - Kaden SCL 1111 Joint Venture$3,368,442,21913 December 2012
1112Hung Hom Station and Stabling SidingsLeighton Contractors (Asia) Limited$5,241,356,0857 March 2013
1113Reprovisioning of NTS Animal Management Centre and Shatin Plant Quarantine StationKaden - Leader Joint Venture$132,608,0007 September 2012
1114Pedestrian Links at Tsz Wan ShanPaul Y. Construction Company, Limited$608,000,00011 July 2012
1115New International Mail CentrePenta-Ocean Construction Co. Ltd.$703,269,1926 July 2011
1117Pat Heung Depot Modification WorksPaul Y. Construction Company, Limited$810,800,00016 October 2012
1119Trackwork and Overhead Line Modification Works at Lo Wu and Pat Heung DepotChun Wo - Henryvicy - GTECH Joint Venture$105,600,00110 October 2012
1120Trackwork and Overhead Lines for SCL Phase IAlstom Hong Kong Ltd$ 425,910,95418 October 2013
1120BTrackwork and Overhead Lines for SCL Phase 2Contract will be awarded soon
11209Platform Modification and Associated Works at East Rail LineChun Wo Construction and Engineering Co Ltd$835,600,0004 July 2013
1121Cross Harbour TunnelsPenta-Ocean - China State Joint Venture$4,350,000,00010 December 2014
1122Admiralty South Overrun TunnelVinci Construction Grands Projets$412,138,88815 October 2015
1123Exhibition Station and Western Approach TunnelLeighton - China State Joint Venture$5,869,282,299.9515 January 2015
1124Admiralty SCL Related WorksLeader – Kaden SCL1124 Joint Venture$833,606,00010 Mar 2016
1125Police Sports and Recreation Club Enhancement WorksSun Fook Kong Construction Ltd $297,000,00013 December 2013
1126Reprovisioning of Harbour Road Sports Centre and Wan Chai Swimming PoolKaden-Leader Joint Venture$871,022,80816 Jan 2014
1128Causeway Bay Typhoon Shelter to Admiralty TunnelsDragages-Bouygues J.V.HK$5,266,570,173.0218 August 2014
1129SCL - Advance Works for NSLHsin Chong Construction Co Ltd$299,938,96016 Jan 2014
1141ANew Rolling Stock for SCL Phase 1Changchun Railway Vehicles Co., Ltd$1,139,955,43511 December 2013
1141BNew Rolling Stock for SCL Phase 2Hyundai Rotem Company$4,077,535,44014 December 2012
1151Rolling Stock Modification and New Train Cars for SCL Phase 1Itochu-Kinki Sharyo-Kawasaki Consortium$1,181,077,17311 December 2013
1152Signalling System for SCL Phase 1 & Signalling System Modification for MOL and WRLThales Transport & Security (Hong Kong) Limited$642,526,5055 July 2013
1152BSignalling System for SCL Phase 2Siemens Limited$845,134,91314 December 2012
1153Tunnel ECS for SCL Phase 1Shinryo Corporation$188,992,28312 August 2013
1153BTunnel ECS for SCL Phase 2Contract will be awarded soon
1154Platform Screen Doors for SCL Phase 1 & APG Retrofit for MOLGilgen Door Systems AG$415,870,57814 December 2012
1154BPlatform Screen Doors for SCL Phase 1 & APG Retrofit for EALShenzhen Fangda Automatic System Co., Ltd.$511,666,06616 May 2016
1155Power Supply System and Trackside Auxiliaries for SCL Phase 1GTECH-KUM SHING Joint Venture$208,380,0005 June 2013
1155BPower Supply System and Trackside Auxiliaries for SCL Phase 2CLP Engineering Limited$150,863,8588 December 2014
1159Lifts for SCL Phase 1OTIS Elevator Company (H.K.) Limited$72,194,8428 October 2013
1162TETRA System for SCL Phases 1 & 2Motorola Solutions Asia Pacific Limited$131,436,64112 April 2013
1162BRadio Distribution Network System for SCL Phases 1 & 2Contract will be awarded soon
1163AFC System and SAM System for SCL Phases 1 & 2Kaba Security System (China) Co., Ltd. – Wincard Security System (Beijing) Co., Ltd. Consortium$113,497,6208 December 2014
1164Building Services for Diamond Hill StationGammon E&M Limited$272,000,0004 March 2014
1165Building Services for Hin Keng Station, Ma Chai Hang Ventilation Building and Fung Tak Emergency AccessGammon E&M Limited$219,000,00011 February 2014
1166Main Control System for SCL Phase 1Siemens Limited$308,499,2205 June 2013
1168Train Wash Plant for SCL Phase 1Contract will be awarded soon
1169Communications System for SCL Phase 1Siemens Limited$431,299,43023 August 2013
1172Escalators for SCL Phase 1ThyssenKrupp Elevator (HK) Limited$180,438,0815 September 2013
1172BLifts and Escalators for SCL Phase 2Contract will be awarded soon
1173Building Services for Hung Hom Station and Hung Hom Stabling SidingsShinryo Corporation$631,480,46614 January 2014
1175Building Services for Kai Tak StationLeighton M&E Limited$157,879,8657 January 2014
1176Building Services for To Kwa Wan Station and Ancillary BuildingLeighton M&E Limited$183,341,3204 March 2014
1177Building Services for Ma Tau Wai Station and Ancillary BuildingBEST 1177 Joint Venture$250,310,8368 April 2014
1180ACommunications System Modification for Hung Hom ReprovisioningShun Hing Systems Integration Co., Ltd.$9,721,7348 June 2012
1183EAL Signalling System Modification for SCLAlstom Hong Kong Limited$115,076,0847 August 2012








For reference:

 XRL Contracts Awarded (as of December 2012)

Contract
Scope of Works
Contractor(s)
Awarded Amount
Date Awarded
802
Nam Cheong Property Foundation Removal and Reprovisioning
Hsin Chong Construction Co Ltd
HK$333,888,000
27 Jan 2010
803A
West Kowloon Terminus Diaphragm Walls (Site A)
Bachy Soletanche Group Ltd
HK$461,238,912
27 Jan 2010
803B
West Kowloon Terminus Piles (Site A - North )
Tysan Foundation Ltd
HK$497,348,655
10 Mar 2010
803C
West Kowloon Terminus Piles (Site A - South)
VIBRO-Chun Wo Joint Venture
HK$321,205,203
27 Jan 2010
803D
West Kowloon Terminus Diaphragm Walls and Piles (WKCD)
Bachy Soletanche Group Ltd
HK$819,053,065
27 Jan 2010
805
Sham Mong Road Obstruction Removal
Paul Y. Construction Co Ltd
HK$159,854,869
27 Jan 2010
810A
West Kowloon Terminus Station North
Leighton - Gammon Joint Venture
HK$8,910,360,529
18 Oct 2011
810B
West Kowloon Terminus Station South
Laing O'Rourke-Hsin Chong-Paul Y. Joint Venture
HK$3,320,618,547
12 Jan 2011
811A
West Kowloon Terminus Approach Tunnel (North)
Bachy Soletanche - Laing O'Rourke Joint Venture
HK$1,039,773,410
3 May 2010
811B
West Kowloon Terminus Approach Tunnel (South)
Gammon - Leighton Joint Venture
HK$2,883,248,075
13 Aug 2010
815A
Supply of Metal Doors and Frames including Ironmongery
The Jardine Engineering Corporation Ltd
HK$99,361,309
9 May 2012
815B
Supply of Signs
Pico Projects (International) Ltd
HK$19,930,474
15 Oct 2012
815C
Supply of Advertising Panels
Program Contractor Ltd
HK$9,792,616
15 Oct 2012
816A
West Kowloon Terminus - Environmental Control System
Shinryo Corporation
HK$782,782,622
9 Dec 2011
816C
West Kowloon Terminus - Electrical Installation
Shinryo Corporation
HK$549,633,887
9 Dec 2011
816D
West Kowloon Terminus - Fire Services, Plumbing & Drainage
Leighton - Chubb E&M Joint Venture
HK$663,640,489
9 Dec 2011
820
Mei Lai Road to Hoi Ting Road Tunnels
Dragages - Bouygues Joint Venture
HK$3,668,903,117
3 May 2010
821
Shek Yam to Mei Lai Road Tunnels
Dragages - Bouygues Joint Venture
HK$1,383,895,720
12 July 2010
822
Tse Uk Tsuen to Shek Yam Tunnels
Leighton Contractors (Asia) Ltd
HK$3,235,352,722
10 Mar 2010
823A
Tai Kong Po to Tse Uk Tsuen Tunnels
Maeda - China State Joint Venture
HK$1,502,491,297
12 July 2010
823B
Shek Kong Stabling Sidings & Emergency Rescue Sidings
Maeda - China State Joint Venture
HK$3,218,246,984
20 Oct 2010
824
Ngau Tam Mei to Tai Kong Po Tunnels
Kier-Kaden-OSSA Joint Venture
HK$1,514,862,127
13 Aug 2010
825
Mai Po to Ngau Tam Mei Tunnels
Penta-Ocean Construction Co Ltd
HK$1,683,621,419
27 Jan 2010
826
Huanggang to Mai Po Tunnels
CRCC-HC-CR15G Joint Venture
HK$1,690,866,688
10 Mar 2010
830
Trackwork and Overhead Line System
Chun Wo - CRGL - QR Joint Venture
HK$1,168,655,709
6 July 2011
840
Express Rail Link: Rolling Stock
CSR Qingdao Sifang Co Ltd
HK$1,744,017,141
7 Mar 2012
841A
Signalling System - Trackside Equipment
Beijing HollySys Co Ltd
HK$307,820,668
7 Mar 2012
841B
Signalling System - Trainborne Equipment
Beijing HollySys Co Ltd
HK$182,072,746
7 Mar 2012
843
Tunnel Environmental Control System
GAS Joint Venture
HK$259,852,647
3 May 2011
846
Trackside Auxiliaries
Shinryo Corporation
HK$294,647,850
10 Aug 2011
847
Lifts
KONE Elevator (HK) Ltd
HK$175,116,391
6 Sept 2011
848
Escalators and Moving Walkways
ThyssenKrupp Elevator
HK$90,650,037
6 Sept 2011
850
Passenger Mobile Communications System
Comba Telecom Ltd
HK$105,332,876
12 Dec 2012
852
Ticketing System
Nuctech Company Ltd
HK$165,658,528
16 Apr 2012
853
Main Control System
Beijing HollySys Co Ltd
HK$65,600,000
8 Nov 2011
855
Building Services for Tunnel Ventilation Facilities and Emergency Rescue Siding
ATAL Engineering Ltd
HK$297,396,713
12 Jan 2011
856
Building Services for Shek Kong Stabling Sidings
ATAL Engineering Ltd
HK$140,414,044
1 Feb 2011
861A
Locomotives and Flat Wagons
Jiangsu KTK Locomotive & Rolling Stock Co Ltd
HK$78,286,355
13 Mar 2012





G. Technical Information and Publications:
1. Design standards and manuals
b. NWDM by MTRCL
c. Design Manual for Roads and Bridges, Department of Transport, UK

2. Tunnelling

General:
a. Introduction of construction methods for tunneling works, including Drill-and-Blast method, Cut-and-Cover method, Tunnel Boring (TBM) or Immersed Tube Tunnel.
c. Video of TBM
d. Application and Practice of GFRP Bars in the TBM Launching Shaft of Metro in China, 2007

TBM ground control:
e. Ground Control for Slurry TBM Tunnelling, GEO Report 249

3. Deep excavation
c. Tunnels and deep excavation by Jean Venables, ICE

4. Assessment of adjacent existing buildings

 5. Blasting Control
a. Mines - Explosives and Blasting Control- Mines Division of CEDD

6. Publications from Society

 7. Control of Excavation Works

8. Accident review related to tunneling
a. National Transport Safety Board (2007) Highway Accident Report, Ceilling Collapse in the Interstate 90 Connector Tunne, Boston, Massachusetts

9. Risk Management
a. Risk Management – An Overall View of Geotechnical Baselines Report