I. Blasting Assessment Report shall include:-
II. Typical methods and limits to be applied:-
e. WSD Instruction No. 1038; and
f. MTRC M&W Specification for Structures and Utilities 5;
III. Mines Division Guidance Note on How to Apply for a Blasting Permit:
a. Regulation 46 of the Dangerous Goods (General) Regulations, no person shall carry out any blasting without the permission of the Commissioner of Mines;
b. Pre-Contract Blasting Assessment prepared by Designer and reviewed by CEDD (GEO and Mines Division) and BD (for private projects);
c. Contractor prepares updated Blasting Assessment and submits to CEDD (GEO and Mines Division) and BD (for private projects) for approval;
d. Contractor prepares his Method Statement for Blasting; and
e. Contractors Blasting Assessment and Method Statement are required as supporting documents for the Contractors application for a Blasting Licence and Blasting Permit;
Reference: